Had Design Demonstration
Progress:
Robot can detect the grid and move (needs computer to send commands though)
Beacon Mechanical Design is complete
Chassis Design is complete
Challenges:
Robot overshoots sometimes. May need to adjust sensor position.
Goals:
Have PCB delivered by beginning of March
Design Beacon Motor/Sensor communication
Wednesday, February 13, 2013
Tuesday, February 12, 2013
February 12th
Prepared for Integration Demonstration
Progress
Installed sensors onto prototype chassis
Finished preliminary designs of chassis and beacons in SolidWorks
Progress
Installed sensors onto prototype chassis
Finished preliminary designs of chassis and beacons in SolidWorks
Monday, February 4, 2013
February 5th
Met up to talk about Design Demo/IPeer
Progress:
Built a circuit to amplify and filter the IR transmitter/receiver
Built the circuitry in software
Goals:
Build beacon to be accessible from four sides
Build ball catcher on chassis
Achieve a working demonstration by the design demonstration date
Notified everyone to keep up to date on their work on the blog
Progress:
Built a circuit to amplify and filter the IR transmitter/receiver
Built the circuitry in software
Goals:
Build beacon to be accessible from four sides
Build ball catcher on chassis
Achieve a working demonstration by the design demonstration date
Notified everyone to keep up to date on their work on the blog
Subscribe to: